Executive snapshot

  • Deteriorating Brooklyn collapse next to an excavation: a three-story occupied building at Flatbush and Bedford avenues collapsed on November 11 beside a lot permitted for earthwork and support of excavation to 14 ft below grade; at least one person died and at least nine were hurt as of that evening. The cause was not determined. Editorial: confirm preconstruction surveys, monitoring and underpinning on every dig next to an occupied structure. ENR, Brooklyn partial building collapse, Nov 11
  • Cautious Backlog slipped outside data centers: ABC's indicator fell to 8.1 months in October from 8.7; firms without data-center work dropped to 7.6 months while firms with it rose to 11.5. Editorial: bid lists outside mission-critical work will get more crowded. Construction Dive, ABC backlog October 2026, Nov 10
  • Cautious A December hike is close to fully priced: after the October CPI on November 10, CME FedWatch put 88.8% on a 25 bp hike and 11.2% on 50 bp, up from about 72% a week earlier. Editorial: size interest reserves above SOFR's 3.88% (Nov 9). Investing.com via Yahoo Finance, CME FedWatch, Nov 10
  • Deteriorating Input costs are outrunning bid prices: BLS inputs to new nonresidential construction rose 11.9% y/y in September while nonresidential bid prices rose 5.4%, a 6.5-point gap. October PPI is due November 13. Editorial: margin is being absorbed by contractors. BLS PPI WPUIP231200, Sep 2026
  • Deteriorating Metals carry the tariff pass-through: AGC's read of BLS data shows steel mill products +27.6%, copper and brass mill shapes +30% and fabricated structural metal +35% from September 2025 to September 2026. Editorial: hold escalation clauses on metals and electrical. AGC Washington, Construction Inflation Alert, Nov 5
  • Cautious Diesel eased but stays high: $6.127 a gallon on November 9, down 16.5 cents on the week and up 59.7% y/y. Editorial: earthwork and haul bids still need a fuel clause. EIA weekly retail diesel, Nov 9
  • Deteriorating Data-center pauses keep spreading: Oklahoma City and Oakland extended moratoriums on November 10, Boise adopted one the same night, and Fort Worth held its first moratorium hearing, with adoption no earlier than February 23, 2027. Newsweek, cities move on data centers after midterms, Nov 11
  • Positive Megaproject backlog is concentrating: Fluor reported Q3 2026 backlog of $34.3B, up 21% y/y, with record new awards of $10.9B and 25 potential megaprojects averaging $4.5B. Editorial: large-scope subs should map who holds those awards. Construction Dive, Fluor Q3 2026 backlog, Nov 10
  • Neutral Permitting bill moves in the lame duck: on November 10 the Senate adopted the motion to proceed to the permitting bill 62-21. Editorial: a slip to January hands the next version to the new majority. U.S. Senate Daily Press, Nov 10

Market movers

ItemChangeNote
ABC backlog 8.1 mo, -0.6 m/m, Oct 2026 ▼ Firms without data-center work: 7.6 mo. Construction Dive, ABC backlog October 2026, Nov 10
ABC infrastructure backlog 8.7 mo, Oct 2026 ▼ Lowest since May 2025. Contractor, ABC backlog falls to 8.1 months, Nov 10
Dec hike odds (CME) 88.8% for 25 bp, Nov 10 ▲ About 72% a week earlier. Investing.com via Yahoo Finance, CME FedWatch, Nov 10
Nonres input prices (BLS) +11.9% y/y, Sep 2026 ▲ Bid prices +5.4% y/y. BLS PPI WPUIP231200, Sep 2026
U.S. retail diesel $6.127, -16.5c w/w, Nov 9 ▼ Still +59.7% y/y. EIA weekly retail diesel, Nov 9
Copper $6.24/lb, Nov 10 ▼ -6.9% over the month, +23.5% y/y; market reference. Trading Economics, copper, Nov 10

Sector outlooks

SectorOutlookSignal
Data centers Cautious Q3 2026 inventory 73.5 GW with 7.2 GW added; vacancy below 1% (Avison Young). OKC, Oakland and Boise acted on pauses Nov 10. Avison Young, U.S. data center report Q3 2026
Industrial / logistics Neutral Q3 2026 vacancy 6.8% with 76.6 msf absorbed (Cushman); warehouse planning weakened in October (Dodge). Cushman & Wakefield, U.S. industrial Q3 2026
Public / infrastructure Neutral September highway and street spending $150.9B SAAR, +3.9% y/y; ABC infrastructure backlog 8.7 months in October. Census C30, September 2026 (released Nov 2)
Power Positive September power construction spending $191.7B SAAR, +11.1% y/y; Duke proposes billing 75% of agreed large-load demand regardless of use. Census C30, September 2026 (released Nov 2)
Multifamily Deteriorating Q3 2026 vacancy 4.7%, +40 bp q/q (CBRE); September 5+ unit starts 349k SAAR, -25.9% y/y. CBRE, U.S. multifamily Q3 2026
Single-family Cautious September single-family starts 859k SAAR, +2.6% y/y; 30-year rate 7.18% (Nov 5). Census new residential construction, September 2026
Heavy industrial / energy Positive Fluor Q3 2026 backlog $34.3B, +21% y/y, including $7.5B for LNG Canada Phase 2. Construction Dive, Fluor Q3 2026 backlog, Nov 10

Teach Me

Protecting adjacent buildings during excavation

Editorial method: when you dig next to an occupied building, the neighbor's foundation becomes part of your job. Before excavation, document the building's condition; during excavation, measure movement and vibration against set limits; and give the field a written rule for stopping work when a limit is reached. Support of excavation (piles, lagging, bracing, underpinning) is designed by an engineer, but the survey, monitoring and stop rule are what catch a problem in time.

Why it matters. On November 11 an occupied three-story building in Brooklyn collapsed beside a lot permitted for excavation to 14 ft; at least one person died and at least nine were hurt as of that evening, and the cause had not been determined. ENR, Brooklyn partial building collapse, Nov 11

  1. Commission a preconstruction condition survey of every adjacent structure, with photos, crack maps and the engineer's rating, and give it to the excavation-support engineer before design is final.
  2. Set monitoring points (optical targets, crack gauges, tilt meters, vibration monitors) with alert and stop thresholds written into the excavation subcontract.
  3. Read the monitoring on a set frequency during excavation and blasting, and route readings to the engineer of record and the GC superintendent the same day.
  4. Write a stop-work trigger: who can stop the dig, who must be called, and what has to happen before work resumes.
  5. Confirm required special inspections of sheeting, shoring and bracing are scheduled and logged before each lift is excavated.
AI prompt Editorial
You are my excavation risk reviewer. From the attached support-of-excavation drawings, the adjacent-building survey and the monitoring plan, list each adjacent structure, the monitoring points on it, the alert and stop thresholds, the reading frequency and who receives readings. Flag any structure rated poor or fair without underpinning or extra monitoring, and draft the stop-work clause for the subcontract. Mark every assumption.

Strategic watchlist

  • New York City Department of Buildings investigation of the November 11 Flatbush collapse next to a permitted excavation. Editorial: expect tighter adjacent-structure inspections on city digs. ENR, Brooklyn partial building collapse, Nov 11
  • Salem, Oregon council deliberates November 12 on a code change that could bar hyperscale data centers, including the planned Verrus project. Editorial: a code change is harder to reverse than a moratorium. Statesman Journal, Salem data-center code vote, Nov 10
  • Minneapolis council votes November 12 on data-center rules before its moratorium expires November 21. Editorial: rules with conditions would reopen sites. FOX 9, Minneapolis data-center rules, Nov 9
  • BLS October PPI on November 13. Editorial: a second month of input gains above bid prices would confirm the squeeze; re-price bids holding past that date. BLS PPI release schedule
  • Senate amendments and final vote on the permitting bill in the lame-duck session. Editorial: a January slip changes who writes the bill. U.S. Senate Daily Press, Nov 10

Top questions leaders should be asking

  • On every urban job next to an occupied building, who signed the preconstruction survey, what are the movement thresholds, and who stops the dig when one is hit?
  • Which of our 2027 pursuits sit outside data-center work, where ABC says backlog is falling fastest, and how many bidders should we now expect?
  • If SOFR rises 25 to 50 bp after December 9, which loans in our pipeline run short on interest reserve, and who covers the gap?
  • Which fixed-price bids carry metals and electrical at September prices, and do they have an escalation clause before the October PPI lands?
  • Which data-center sites in our pipeline need a legislative approval in a city now weighing a pause, and what is our fallback schedule?

This is an archived issue.

Read today's live briefing or get the full briefing in your inbox every morning — free.

See today's Pulse →   Subscribe free