Costs · BLS through Oct 2026

Contractor inputs +13.3%, bid prices +5.5% on the year. Our scope blend: +5.3%.

Inputs and bid prices are BLS producer price indexes Confirmed. The scope blend is our ten-scope weighting of BLS series Editorial. Below: margin squeeze, escalation factors you can carry into a bid, regional bid prices and diesel by region. Next BLS update: Dec 15, 2026.

Margin squeeze

Are costs outrunning what owners pay?

Inputs to nonresidential construction vs bid prices for new nonresidential buildings, both BLS producer price indexes.

Margin squeeze gauge · Oct 2026

Squeeze: input costs are rising 7.7 points faster than bid prices Deteriorating

+13.3%Inputs to nonresidential construction, YoY (+0.71% m/m)
+5.5%Bid prices for new nonresidential buildings, YoY (+1.84% m/m)

Spread +7.7 pts vs +7.0 pts a month earlier, the 97th percentile of 60 months. Inputs (BLS) ↗ (opens in a new tab) Bid prices (BLS) ↗ (opens in a new tab) Confirmed

What to do with it

When the gap widens, fixed-price work loses margin first.

Spread, input-cost YoY minus bid-price YoY, last 60 months. Five-year range −17.2 pts to +9.7 pts.

  • Carry escalation on fixed-price work bid more than 90 days before buyout. Editorial
  • Shorten quote validity on steel, wood and roofing packages. Editorial
  • Use the escalation table below for the 3, 6, 9 and 12-month factors. Editorial
Bid-ready escalation

Escalation by scope, 3, 6, 9 and 12 months out.

A range for each scope you can carry from bid to buyout. Download the CSV for your estimate.

Bid-ready escalation factors by scope, 3 to 12 months
Scope12-mo actual3 mo6 mo9 mo12 moTrend
Structural steel and metals Editorial+10.8%2.6–3.6%5.3–7.3%8.0–11.2%10.8–15.2%Accelerating
Plumbing and HVAC Confirmed+5.1%1.3–2.4%2.5–4.8%3.8–7.3%5.1–9.8%Accelerating
Sitework and paving Editorial+6.9%1.7–2.0%3.4–4.1%5.1–6.2%6.9–8.3%Accelerating
Wood and framing Confirmed+6.4%-0.9–1.6%-1.7–3.1%-2.5–4.7%-3.4–6.4%Steady or easing
Roofing and envelope Confirmed+4.9%1.2–1.4%2.4–2.8%3.6–4.2%4.9–5.7%Accelerating
Concrete Confirmed+5.5%1.2–1.3%2.5–2.7%3.8–4.1%5.0–5.5%Steady or easing
Field labor (wages) Confirmed+4.7%1.2%2.3–2.5%3.5–3.8%4.7–5.0%Accelerating
Electrical Confirmed+3.3%0.8–1.1%1.6–2.3%2.5–3.4%3.3–4.6%Accelerating
Masonry Editorial+4.4%1.0–1.1%1.9–2.2%2.9–3.3%3.9–4.4%Steady or easing
Drywall and interiors Editorial+2.7%0.7–1.1%1.4–2.1%2.0–3.2%2.7–4.3%Accelerating

How to read: each range runs from the trailing 12-month rate to the 6-month annualized rate, compounded over the horizon, so the low end assumes last year repeats and the high end assumes the recent pace holds. BLS data through Oct 2026. Ranges are our arithmetic, not a forecast Editorial. Basis for each row is in the CSV. Download CSV ↓

Bid prices by region

Where owners are paying the most more.

Nonresidential building bid prices by region
RegionBid price YoYMonthSource
Northeast+6.0%Oct 2026BLS ↗ (opens in a new tab) Confirmed
South+5.7%Oct 2026BLS ↗ (opens in a new tab) Confirmed
Midwest+4.9%Oct 2026BLS ↗ (opens in a new tab) Confirmed
West+5.8%Oct 2026BLS ↗ (opens in a new tab) Confirmed

BLS producer price index for new nonresidential building construction, by Census region. It measures what owners pay general contractors, so it shows where bid pricing is firmest.

Selling-price cross-check

Independent reads on what owners are paying, and next year’s band.

Contractor and cost-consultant indexes next to the BLS bid-price index, plus one published 2027 forecast (Directional). When the measured reads agree, the bid-price trend is solid; when they split, ask why.

Turner Building Cost Index · Q3 2026
1575

+5.49% YoY; +1.48% q/q

National selling-price index (labor, materials, market competition). Compare with the BLS bid-price index for new nonresidential buildings shown alongside. Turner Construction ↗ (opens in a new tab) Confirmed

Released Oct 13 · next: Q4 2026, mid-January

RLB National Construction Cost Index · Jul 2026
292.28

+4.45% YoY; +1.28% q/q

Cost consultant’s national construction cost index (base April 2001 = 100). Rider Levett Bucknall ↗ (opens in a new tab) Confirmed

Released Sep 28 · next: Q4 2026 report

JLL U.S. tender price forecast · 2027
3.1–4.2%

2027 forecast; 2026 forecast 3.5–4.6%

Forecast of the prices contractors bid, not a measured index: plan 2027 escalation inside this band, which JLL says is above the pre-2020 norm in every region. Compare with the measured BLS bid-price trend alongside. JLL ↗ (opens in a new tab) Directional

Released Nov 12 · next: JLL mid-year update

BLS bid prices, new nonresidential buildings · Oct 2026
+5.5%

YoY, producer price index

What owners pay contractors for new warehouses, schools, offices, industrial and health care buildings. BLS ↗ (opens in a new tab) Confirmed

Diesel

Fuel, priced by region.

Diesel by region · week of Nov 23

$5.695 is the national average. West Coast (PADD 5) runs $1.42 above Gulf Coast (PADD 3).

On-highway diesel by EIA PADD region
Region$/galWeekYoYSource
U.S. average$5.695−24.2¢+48.7%EIA ↗ (opens in a new tab)
East Coast (PADD 1)$5.619−16.3¢+45.5%EIA ↗ (opens in a new tab)
Midwest (PADD 2)$5.671−29.6¢+47.3%EIA ↗ (opens in a new tab)
Gulf Coast (PADD 3)$5.294−25.3¢+53.1%EIA ↗ (opens in a new tab)
Rocky Mountain (PADD 4)$5.772−23.9¢+55.0%EIA ↗ (opens in a new tab)
West Coast (PADD 5)$6.709−23.9¢+48.6%EIA ↗ (opens in a new tab)

EIA weekly retail on-highway No. 2 diesel Confirmed. Equipment hours: at an illustrative 8 gal per machine hour, the $1.87/gal rise since last year adds about $15 per machine hour Editorial. Earthwork and hauling carry the most fuel exposure; price fuel by the job’s region, not the national average.

Blended cost of construction · BLS data through Oct 2026

What it costs to build, and which scope is moving it.

Ten scopes of work, five years each, rebased to Sep 2021 = 100. Click a scope to drill in, or set the weights to your own estimate. Next BLS update: Dec 15, 2026.

Scope blend · year over year
–

Scopes of work · click to drill in

Bars show each scope’s 12-month change; the dot shows how many points it added to the blend. Weights are an illustrative commercial split, not data: set them to your estimate. Editorial

Text summary: the scope blend is +5.3% over 12 months and +29.4% since September 2021 (index 129.4). The BLS materials index is +11.5%. Steel, mep, field supply 47% of the year’s increase.

Free · every weekday

Escalation and margin squeeze, every weekday.

The same figures in the free daily briefing, with sources on every number.

Free daily briefingNo cardUnsubscribe in one click